ビル進捗状況 – Bldg. Progress

UPDATE: APRIL 7, 2023

Here you will find the church building renovation progress as well as opportunities to be involved through the process.

OPORTUNITIES TO SERVE

  1. Clean up
  2. Wallpaper removal
  3. Old pipe removal
  4. Old tile removal
  5. Carpentry work
  6. Plumbing work
  7. Painting
  8. Assembling cabinets

 

DONE…

  1. Internal old walls removal. √
  2. Major water lines fixed. √
  3. Trash taken to construction debris disposal site. √
  4. Estimates from several companies for various jobs. √
  5. Asbestos analysis for ceiling panels. √
  6. Removal of 1F old ceiling panels. √
  7. 2F ceiling removal √
  8. Old A/C freon gas removal √
  9. Old A/C removal √
  10. Various concrete cutting jobs √
  11. Rough plumbing √
  12. Window glass replacement √
  13. Restroom floor tile √
  14. Water gas heater √
  15. New room floor steel beam √

 

NEXT STEP…

  1. A/C gas removal. Getting estimates from companies for proper removal.
  2. Getting/awaiting some estimates (bathrooms, window glasses, electrical, AC).
  3. Electrical. (In progress)
  4. Plumbing.
  5. Air Conditioners. (Getting estimates)
  6. Carpentry. (In progress)
  7. Paint. (April 24th ~)
  8. Flooring.  (May 1 ~)
  9. Furnishing.  (May 8th~)
  10. Sound system. (May 17th~)
  11. Inside windows 内窓. (~June 5th)
  12. Inauguration ceremony: Sunday, May 21 (More details soon!)